Impacted services: None
Expected impact: Low, planned maintenance
On 03-02-2026 between 0900 - 0930 (CEST) we will perform a test on our emergency power supply infrastructure.
We will test if the generator at Tuxis-1 operates within parameters.
This will not affect any services nor power supply to Tuxis-1.
Further tests will not be announced since they are part of our regular maintenance.
And will take place every first Tuesday of every month.
[Update 1]
09:00, The Generator has successfully started and will run for 30 minutes.
Another update will be posted when we switch back to mains-power at 09:30.
[Update 2]
09:45, We successfully switched back to mains-power at 09:30 and everything is stable and the generator operated within parameters.
We will now close this issue.